Dear clients,
Please beware that Markley Group, the building operator for 1 Summer Street
data center facility in Boston, will be performing a prenventive maintenance
on electrical bus risers starting at 10 PM (EDT GMT-4) on Friday, April 11th.
The electrical loads serving colocation floors will be transferred to UPS
batteries first, then generators will take over the load for the remaining
duration of the maintenance after they come online.
There is no service impact expected to customers as a result of this maintenance
however because the work is being conducted on electrical systems, this notice
should be considered as a precaution in case of unlikely outages.
If you experience any problems connecting or with your equipment during the maintenance window,
please contact 1-617-459-4051 extension 500.
Thank you,
Change Management